Frederick High School

Frederick High School

Outstanding Problem-Solving Leads To A New School Opening On Time

Kaempf & Harris started working on the new Frederick High School in January, 2016 and completed it in June 2017. Manpower peaked at 20 people, which allowed the school ample time to open in September 2017.

The school used more than 600,000 pounds of galvanized ductwork and16,000 pounds of solid welded stainless steel that serves 25 air handler units, 67 fans, 5 make-up air units and 113 heat pumps. Kaempf & Harris installed 6 mechanical rooms; 1,500 registers, grilles and diffusers; and 305 fire and fire/smoke dampers. The building met LEED Silver standards for environmentally friendly operations.

Kaempf & Harris’ field foreman and management team received praise from the construction manager and the owner for their outstanding efforts in constructability, development and implementation of problem-solving ideas during the project.

Now, the new high school is a 3-story facility with more than 270,000 square feet and has a capacity for 1,826 students.

Project Stats

Project Type

New Construction, High School, Modern Structures

Project Specs

270,000 Square Feet

General Contracting Partner

Oak Contracting

Mechanical Contracting Partner

Warner Mechanical

Location

Frederick, Maryland

 A utility room with large air ducts and metal equipment.
No items found.
No items found.
 A utility room with large air ducts and metal equipment.
 A building rooftop with multiple ventilation pipes.
A cluttered industrial room with lots of pipes and machinery.
No items found.

Contact Us for Your Metal Fabrication Needs

Have questions about metal fabrication or installation? We’re happy to start a conversation!

Contact Us
Featured Project

Hagerstown Multi-Use Sports Event Center

In October of 2021, the Maryland Stadium Authority authorized and issued $59.5 million to construct a new Multi-Use Sports Event Center in downtown Hagerstown.